Owner: NJDOT | Client: AECOM | Mercer County, NJ

Project Statistics

Location: Borough of Woodstown
Completion Date: January, 2020
Size: 0.49 Miles
Construction Cost: $2.2 Million
Project Manager: Samir D. Mody, PE
Inspector: Ayo Saba, NICET III
Contact: Joseph Mellace
Resident Engineer
NJDOT
609-941-8151

Keller Engineers administered the inspection, reporting, and acceptance of this Federally-funded roadway resurfacing, restoration and rehabilitation of Route US 40. Project is 0.49 miles in length and encompasses the eastbound and westbound directions.

Keller Engineers responsibilities included the oversight and QA/QC of inspecting the following construction activities: maintenance and protection of traffic for mainline and secondary roadway lane closures; pavement removal; HMA milling; tack and prime coats; placement of HMA intermediate, base and surface courses (12.5M64, 25M64, and 12.5ME respectively); core samples HMA; IRI testing for rideability; utility relocations; excavation; new drainage pipes and inlets; reset gas and water valves; sewer pipes and reconstructing handicap curb ramps in accordance with current ADA regulations.
In addition, Keller provided the RE with technical support, responses to contractor e-mails, requests for extra work and as-builts. Other administrative responsibilities included the preparation of inspection reports, review of certified payrolls for prime and subcontractors, review of EEO documentation and providing the RE with quantities for the monthly payment vouchers. Reporting was saved into the Site Manager System.