Owner: NJDOT | Burlington and Ocean Counties, NJ

Project Statistics

Location: Woodland Barnegat
and Stafford Townships
Construction: 6-2019 to 6-2020
Size: 18.4 Miles
Construction Cost: $4.6 Million
Project Manager: Samir D. Mody, PE
Inspector: Edward Riordan
Closeout: Ramon Melo, NICET III
Contact: Mark Loughery Resident Engineer
NJDOT
Region South Construction
One Executive Campus
Route 70 West
Cherry Hill, NJ 08002
609-820-2864 (cell)

Field responsibilities and duties included on-site inspection of the contractor’s means and methods for maintenance and protection of traffic, roadway excavation unclassified, backfilling, reconstruction of subgrade and subbase, widening of existing shoulders, milling, resurfacing, placement of WMA and HMA of varying thickness, sealing of reflective cracks in bituminous pavement, application of temporary and new pavement markings, installation of sanitary sewer, water and storm sewer mains and structures, replacement of curb and sidewalk, reconstructing handicap curb ramps and sidewalk in accordance with current ADA regulations and other incidental construction activities.

Administrative duties include the preparation of inspection reports, quantity measurements, extra work orders, final inspection, and resolution of punch-list activities, computations and supporting documentation for monthly pay estimates. The project is being performed with both day-time and night-time operations.